• ABOUT
  • PRODUCTS
  • CASE STUDIES
  • NEWS
  • CONTACT
  •  

    Major NE Coast Oil Refinery Cat Cracker

    Location: Northeast USA

    Industry: Oil and Gas/Refineries

    A corroded and leaking underground 25" carbon steel cooling water pipe. Due to the leak, the cat cracker was not operational. Every day the Cat Cracker is not operational results in an approximate loss of one million dollars.

    Read More


    Challenge

    A corroded and leaking underground 25" carbon steel cooling water pipe. Due to the leak, the cat cracker was not operational. Every day the Cat Cracker is not operational results in an approximate loss of one million dollars.


    Solution

    An effective yet efficient solution was required so the refinery could return the cat cracker to service. After digging up the pipe a belly clamp was constructed to encapsulate the damaged pipe section.

    The clamp had a 4" stand off from the damaged section of pipe. Due to occasional temperature spikes between 250°F and 300°F SC5400 paste was used to seal the clamp. After the clamp to the pipe was sealed and the clamp was filled with the SC5400 paste and allowed to set.

    As an extra layer of protection, the entire clamp was then wrapped with a cloth mesh fabric infused with SC5400. The corroded, leaking pipe was repaired and restored and the cat cracker was returned to service in record time.

    The Novocoat team saved the refinery millions in lost revenue.


    Pima County Wastewater Treatment Plant

    Location: Pima County, USA

    Industry: Water/Waste Water

    Wastewater Treatment Facility Finds a cure for Deteriorated Concrete.

    Read More


    Challenge

    The Roger Road Wastewater Treatment Plant had an expensive problem: a severely deteriorated concrete splitter box needed to be repaired, but before any work on this operating structure could begin, a temporary but costly "pump around facility" had to be installed to handle the process performed by the splitter box, says John Munden, Civil Engineering Manager with the Pima County Wastewater Management Department.

    The splitter box is used to split the flow of raw sewage and direct it to various primary clarifiers, he says. The structure was to have been part of a larger project to rehabilitate other concrete structures with a calcium aluminate cement underlayment and epoxy topcoat, but the contractor handling that job declined to take on the splitter box, declaring that it couldn't be fixed, says Allen Kauffman, the president of another contracting firm that subsequently did the work using a polymer concrete repair product and an epoxy novolac lining.

    The covered splitter box is 8 ft (2.4 m) wide, 18 ft (5.4 m) long, and divided into two sections of different heights to aid in sewage separation. The turbulent contents of the splitter box encourage the development of hydrogen sulfide gas and the subsequent growth of microorganisms that attack the concrete substrate, says Kauffman. In addition, says Munden, the cover exacerbates the hydrogen sulfide problem by trapping the gas, increasing its concentration in the structure.

    The deterioration of the splitter box was extensive, but not uniform, says Munden. In some areas affected by sulfuric acid attack, the concrete had lost over 50% of its original thickness. Concrete had been eaten away, exposing rebar. One wall, originally 12 in. (30.5 cm) thick, was reduced to a three-inch (7.6-centimeter) thickness, says Kauffman. The rebar in some areas had been completely corroded, he adds.


    Solution

    Given twelve days to do the work in November 2003, Kauffman's company began the project by power washing the splitter box at 3,500 psi (233 bar) to clean the concrete surface and remove loose material. The deteriorated areas were then abrasive blasted with copper slag. The contractor installed a new mat rebar system, securing it to concrete with drilled-in dowels or tying it to the existing rebar. The contractor then performed another power wash with an injection of a soluble salt treatment. Blowers were set up to speed drying, and six hours later, the contractor began applying the polymer concrete repair product by trowel.

    Working on one wall section at a time, the contractor applied the polymer concrete repair product in approximately two-inch (five-centimeter) thick layers, says Kauffman. The concrete repair material was allowed to set up for two hours before additional layers were applied. The contractor built the walls of the concrete structure back to their original thicknesses, in some cases taking a 1/8-inch-thick (3 mm) area back to 10 in. (25 cm). The contractor performed adhesion tests on the concrete repair product, noting that the cementitious substrate failed b e fore the polymer concrete repair product.

    The surface preparation, rebar installation, and rebuilding of the concrete took four days, says Kauffman. Forced heat aided the cure of the concrete repair material, allowing the contractor to proceed with the lining application 12 hours later. Over two days, two coats of the chemical-resistant epoxy novolac lining were applied by brush and roller to a total thickness between 30 and 35 mils (750 and 875 micrometers). The epoxy novolac was heat cured over the first night and then heat cured for 24 hours following the final application, says Kauffman. According to Kauffman, Pima County had an inspector on site during all working hours.

    The concrete splitter box rehabilitation was completed in less than 7 days, saving more money in "pump around facility" expenses than it cost to perform the work, says Kauffman. The contractor performed a follow-up inspection in March 2005, noting no signs of deterioration of the system. Munden says that, although a formal follow-up inspection has not been conducted on the operating splitter box, the lining system appears to be holding up well. He adds that the many of the metal components of the splitter box have been replaced and that it is slated for the installation of a ventilation system for odor control and hydrogen sulfide mitigation. Opt Co. (Gilbert, AZ) performed the surface preparation and underlayment and lining application. Novocoat (Addison, TX) manufactures the polymer concrete repair material and the epoxy novolac lining. Hold Tight Solutions Inc. (Houston, TX) manufactures the soluble salt treatment.


    Ina Road Road Wastewater Expansion Project

    Location: Tuscon, Arizona - Pima County

    Industry: Water/Waste Water

    The Ina Road Wastewater Treatment Facility expanded to double in size. Among the many needs of the expansion project was to ensure that the new infrastructure was protected for many years to come, allowing the maximum life for the anoxic basins, aeration basins, skimmer house primary clarifiers and influent and bypass channels.

    Read More


    Challenge

    The Ina Road Wastewater Treatment Facility expanded to double in size. Among the many needs of the expansion project was to ensure that the new infrastructure was protected for many years to come, allowing the maximum life for the anoxic basins, aeration basins, skimmer house primary clarifiers and influent and bypass channels. It was imperative the coating selected to protect these structures would be able to withstand the chemical and hydrogen sulfide gas attack.


    Solution

    After careful review and selection, Novocoat SP2000R was chosen by third party engineers as the Category A coating, where the toughest protection was required. Over 13,000 gallons of product was applied to the anoxic basins, aeration basins, skimmer house clarifiers and the influent/by pass channels.

    The project also utilized Novocoat?s line of sealers, primers, and pastes to complete the coating phase of the multi-year project.


    Major NE Coast Oil Refinery Valve Box Headers 1

    Location: North East USA

    Industry: Oil And Gas/Refineries

    The problem here was a valve box header leak. The main cooling water header used to cool the poly-alky unit had developed a major leak. The pipe could not be repaired because the valves used to isolate the pipe leak were not functioning properly.

    Read More


    Challenge

    The problem here was a valve box header leak. The main cooling water header used to cool the poly-alky unit had developed a major leak. The pipe could not be repaired because the valves used to isolate the pipe leak were not functioning properly.


    Solution

    The Novocoat Team went in and performed an emergency pipe encapsulation using fiberglass mesh infused with SP2000R to abate the water heat. The poly unit was able to continue to operate at full power, eliminating the need to shut the unit down for pipe replacement.

    The cost savings to the refinery were estimated in the hundreds of thousands of dollars.


    Major NE Coast Oil Refinery Valve Box Headers 2

    Location: North East USA

    Industry: Oil And Gas/Refineries

    Concrete encased pipe and valve body had developed a severe leak. The leak was unable to be repaired with conventional pipe wrap methods. Major NE Coast Oil Refinery was faced with a costly replacement.

    Read More


    Challenge

    Concrete encased pipe and valve body had developed a severe leak. The leak was unable to be repaired with conventional pipe wrap methods. Major NE Coast Oil Refinery was faced with a costly replacement.


    Solution

    Novocoat was able to provide a quick and economical solution. The quick set R200 was used to stop active leaking. Next, a wood box was constructed around the entire valve body and damaged pipe. The box was then filled with a mixture of SC1100 and sand to completely encapsulate the valve and the pipe. The pipe and valve body were repaired and leak free.

    Major NE Coast Oil Refinery maintenance called the project a complete success saving valuable time and realizing significant cost savings to the operation of the unit.


    Six Flags Great Adventure Dolphin Tank

    Location: Jackson, New Jersey

    Industry:Miscelaneous

    Six Flags maintenance workers were faced with transforming a corroding pool into a safe, repaired, and attractive dolphin tank. Due to the rusted re-bar and the deteriorating concrete, restoring the tank seemed an impossible feat. Because concrete will not bond to itself again during repair, it meant that the concrete would have to be replaced entirely as well as removing and replacing the re-bar.

    Read More


    Challenge

    Six Flags maintenance workers were faced with transforming a corroding pool into a safe, repaired, and attractive dolphin tank. Due to the rusted re-bar and the deteriorating concrete, restoring the tank seemed an impossible feat. Because concrete will not bond to itself again during repair, it meant that the concrete would have to be replaced entirely as well as removing and replacing the re-bar. Additionally, the tank needed to be covered with a protective coating that would adhere to concrete and was NSF/ANSI 61 certified.


    Solution

    Novocoat products were easily able to fix the tank issue without complete concrete and re-bar removal and replacement. First, the concrete substrate was grit blasted, causing all failed concrete to break loose. The re-bar was treated with Novocoat?s RUSTSTOPPER to stop further rust. The concrete was then repaired with NOVOLITE and T-FLOOR which bonds tenaciously to the concrete creating a lasting and permanent bond.

    Because the concrete repairs were done with a novolac epoxy, the material was cured completely the same day, as opposed to the 28 day cure time concrete requires. Last, the entire dolphin pool was top coated with SP2000 tinted blue. SP2000 resists the corrosive salt water within the dolphin tank and it is NSF/ANSI 61 certified.

    Six Flags was impressed with not only the ability to successfully repair and beautifully coat the tank, but the efficient and expedited down time from start to finish.


    Kimberly Clark

    Location: Knoxville, TN

    Industry: Pulp and Paper

    At Kimberly Clark's paper mill, piping was leaking. Despite the fact that the stainless steel piping was coated with other epoxies and coal tar coatings, the wet paper slurry had created a thriving environment for a microbial attack. The microbial attack resulted in tiny pinholes causing the stainless steel piping to leak. The maximum piping life in this corrosive environment was only six months.

    Read More


    Challenge

    At Kimberly Clark's paper mill, piping was leaking. Despite the fact that the stainless steel piping was coated with other epoxies and coal tar coatings, the wet paper slurry had created a thriving environment for a microbial attack. The microbial attack resulted in tiny pinholes causing the stainless steel piping to leak. The maximum piping life in this corrosive environment was only six months.


    Solution

    Kimberly Clark desperately needed a protective coating that would withstand the aggressive microbial attack. Because other coatings had not provided much success, only a small section of piping was initially lined with SC3000Y to see if it would withstand the service. Six months later the piping was inspected. Much to their surprise, the piping looking the same as the day of installation with no pinholes, and no leaks. At the Kimberly Clark plant, all replacement piping is now lined with SC3000Y.

    Novocoat SC3000Y has provided a leak free solution and cost efficient solution to the harsh microbial attack.


    The Bellagio Hotel

    Location: Las Vegas, Nevada

    Industry: Miscelaneous

    To provide long term corrosion protection to piping, pumps, and metallic surfaces of bridges for walkways around the manmade lake and dancing water fountain. In addition, Bellagio management wanted material to be subdued color wise, so as not to take away from the beauty of the lake and fountains.

    Read More


    Challenge

    To provide long term corrosion protection to piping, pumps, and metallic surfaces of bridges for walkways around the manmade lake and dancing water fountain. In addition, Bellagio management wanted material to be subdued color wise, so as not to take away from the beauty of the lake and fountains.


    Solution

    The decision was made by the architect and engineers that NOVOCOAT SP2000 was the best choice for long term protection and the color of near black was chosen to make the coating obscure.

    Eight years after installation, SP2000 continues to provide protection to the valuable piping, fountain, and water future of the beautiful Bellagio Hotel.


    Cooling Tower Leak Repair

    Location: Richardson, Texas

    Industry: HVAC

    The cooling tower for an office building in Richardson, Texas was leaking hundreds of gallons of water and needed to be replaced. While the office building was closed over July fourth weekend in 1996, the repair crew had 48 hours to repair the leaks in the basin, completely recoat the inside and outside of the basin and the entire structure, including insulated piping and hot boxes, and in the end, to return the structure to full operating status.

    Read More


    Challenge

    The cooling tower for an office building in Richardson, Texas was leaking hundreds of gallons of water and needed to be replaced. While the office building was closed over July fourth weekend in 1996, the repair crew had 48 hours to repair the leaks in the basin, completely recoat the inside and outside of the basin and the entire structure, including insulated piping and hot boxes, and in the end, to return the structure to full operating status.


    Solution

    The inside surface of the basin was prepared for coating with a light blasting of the surface, the holes were repaired using a polymer mesh and Novocoat EC306 paste with an immediate flood coat of SP2000R to seal and protect the basin substrate. In addition, SP2000R was used to coat all other surfaces and the job was completed within thirty-six hours.

    Ten years later the cooling tower is still operating in satisfactory condition. The life of the cooling tower has been extended by double at a cost of approximately 15% of the replacement cost.

    There are hundreds of other cooling towers across the U.S.A. with a similar story line where SP2000R saved the day.

     

    PHOTO GALLERY

    01 02 03 04 05 06 07 20 24 10 11 12 13 14 15
    • SP-2000W ID steel pipe
    • Manhole coated with SL-100
    • Top coat of SC-3300 on splitter box
    • Splitter box erossion repair using Novolite<br/> concrete repair
    • SL-100 being hand applied in manhole in Colorado
    • SP2000R manhole bench
    • Finishing touches on manhole useing SP-2000R
    • Impellar Repair
    • Novofloor 1500
    • Novofloor application
    • Propellar housing repair
    • R-200
    • R-200
    • Over the ditch application of R-200 on Petroleum products pipeline
    • Reconstructed wall using Novolite Concrete Repair
    • SP-2350
    • SP-2000R being applied to walls of Skimmer House<br/> in Arizona
    • SP-2350 Primary Clarifier
    • Channel Box - before
    • Channel Box - After